• Connecting the Diemen power plant

Connecting the Diemen power plant

Customer
Tennet TSO

Description
Aansluiting centrale Nuon aan het bestaande net met 380 kV verbinding

Execution period
2012

in Diemen, near Amsterdam, A.Hak Electron connected the new NUON (part of Vattenfall) power plant to the existing energy grid. The project consisted of the construction of three 380 kV connection cables with a 900 meter length, during which two fiberglass cables were also installed.

Across the total trajectory length, over 620 had to be crossed with HDD's (horizontal directional drilling). For this part of the project, sister company A.Hak Drillcon was hired. In order to test the connection cables, A.Hak Electron collaborated with yet another sister company: A.Hak Infranet. The project was completed on-time and compliant with all customer requirements, in an integrated solution delivered by A.Hak.

  • news

    High voltage networks connected High voltage networks connected

    High voltage networks connected

    For customer Reddyn, we connected an existing 150 kV network in the eastern Netherlands with a new 380 kV connection between the Netherlands and Germany.

  • projects

    Replacing switching facilities Replacing switching facilities

    Replacing switching facilities

    Rerouting and replacing existing oil-pressure cables to two new switching stations.

  • projects

    MPP3 power plant Maasvlakte MPP3 power plant Maasvlakte

    MPP3 power plant Maasvlakte

    Construction of a 380kV cable trajectory from the MPP3 power plant to the TenneT station.

  • projects

    High Temperature Conductors for 110kV connection High Temperature Conductors for 110kV connection

    High Temperature Conductors for 110kV connection

    Assembly of High Voltage Conductors into a 110 kV connection